CSI MasterFormat 08 40 00
Levelling glazing and storefront bids in San Diego, CA
Buying glazing and storefront for a project in San Diego? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Engineering, sealant and interior glass are the lines most often missing.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Aluminium storefront
- 2Curtain wall
- 3Entrance doors and hardware
- 4Interior glass and relites
- 5Mirrors
- 6Perimeter sealant
- 7Engineering and shop drawings
- 8Field testing
Usual alternates
- Window film
Where glazing and storefront bids differ
- Engineering and shop drawings excluded from storefront and curtain wall bids.
- Interior glass, relites and mirrors carried by the glazier on some bids and by nobody on others.
- Perimeter sealant assumed to be the waterproofing sub's.
- Field water testing excluded, or limited to one test.
Have the spec section?
The Bid Leveler can draft your scope lines from the project’s own spec, each with the paragraph it came from, so you level against what this job actually requires.
Open the Bid Leveler →