CSI MasterFormat 08 40 00

Glazing and storefront scope checklist for bid levelling

Engineering, sealant and interior glass are the lines most often missing.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Aluminium storefront
  2. 2Curtain wall
  3. 3Entrance doors and hardware
  4. 4Interior glass and relites
  5. 5Mirrors
  6. 6Perimeter sealant
  7. 7Engineering and shop drawings
  8. 8Field testing

Usual alternates

Compared side by side, never in the base total.

  • Window film

Where glazing and storefront bids differ

The gaps worth a written answer from every bidder before award.

  • Engineering and shop drawings excluded from storefront and curtain wall bids.
  • Interior glass, relites and mirrors carried by the glazier on some bids and by nobody on others.
  • Perimeter sealant assumed to be the waterproofing sub's.
  • Field water testing excluded, or limited to one test.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the glazing and storefront template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.