CSI MasterFormat 09 90 00
Painting scope checklist for bid levelling
Exposed structure, doors and frames, and touch-up after punch are commonly left out.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Interior walls and ceilings
- 2Doors and frames
- 3Exposed structure and deck
- 4Exterior painting
- 5Wall coverings
- 6Epoxy floors and coatings
- 7Touch-up after punch list
- 8Lifts and access
Usual alternates
Compared side by side, never in the base total.
- Graffiti coating
Where painting bids differ
The gaps worth a written answer from every bidder before award.
- Exposed structure and deck left out of interior painting bids.
- Doors and frames excluded because they are assumed to arrive factory-finished.
- Touch-up after the punch list limited to one visit or excluded.
- Lifts and access equipment assumed to be supplied by the GC.