CSI MasterFormat 09 21 00
Drywall and framing scope checklist for bid levelling
Insulation, backing and patching after other trades are where drywall bids disagree.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Metal stud framing
- 2Hang and tape
- 3Level 5 finish where scheduled
- 4Acoustical ceilings
- 5Batt insulation in walls
- 6Backing and blocking
- 7Shaft wall
- 8Fire-rated assemblies
- 9Access panels, install
- 10Patch after MEP trades
- 11Clean-up and debris removal
Usual alternates
Compared side by side, never in the base total.
- Upgrade to abuse-resistant board
Where drywall and framing bids differ
The gaps worth a written answer from every bidder before award.
- Batt insulation in walls excluded from drywall bids and missing from the insulation package.
- Backing and blocking assumed to be by rough carpentry or by the trade that needs it.
- Patching after MEP rough-in excluded, which becomes a change order on every job.
- Level 5 finish priced as Level 4 where the finish schedule calls for it.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the drywall and framing template