The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1CMU walls
  2. 2Brick veneer
  3. 3Grout and reinforcing
  4. 4Through-wall flashing and weeps
  5. 5Lintels, set only
  6. 6Control joints and sealant
  7. 7Scaffolding
  8. 8Mortar and cleaning
  9. 9Cold weather protection

Usual alternates

Compared side by side, never in the base total.

  • Stone accents

Where masonry bids differ

The gaps worth a written answer from every bidder before award.

  • Grout and reinforcing in CMU carried by neither the mason nor the concrete sub.
  • Through-wall flashing and weeps assumed to be by the waterproofing or roofing sub.
  • Scaffolding excluded, or priced for one lift less than the elevations need.
  • Lintels set but not furnished, with the steel left to miscellaneous metals.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the masonry template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.