CSI MasterFormat 04 00 00
Masonry scope checklist for bid levelling
Grout, reinforcing and flashing are frequently split between masonry and other trades.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1CMU walls
- 2Brick veneer
- 3Grout and reinforcing
- 4Through-wall flashing and weeps
- 5Lintels, set only
- 6Control joints and sealant
- 7Scaffolding
- 8Mortar and cleaning
- 9Cold weather protection
Usual alternates
Compared side by side, never in the base total.
- Stone accents
Where masonry bids differ
The gaps worth a written answer from every bidder before award.
- Grout and reinforcing in CMU carried by neither the mason nor the concrete sub.
- Through-wall flashing and weeps assumed to be by the waterproofing or roofing sub.
- Scaffolding excluded, or priced for one lift less than the elevations need.
- Lintels set but not furnished, with the steel left to miscellaneous metals.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.