The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Structural steel, furnish
- 2Structural steel, erect
- 3Metal deck
- 4Shear studs
- 5Connection design and engineering
- 6Shop drawings
- 7Miscellaneous metals and lintels
- 8Stairs and railings
- 9Crane and hoisting
- 10Shop primer and touch-up
Usual alternates
Compared side by side, never in the base total.
- Fireproofing
Where structural steel bids differ
The gaps worth a written answer from every bidder before award.
- Connection design and engineering excluded, or assumed to be done by the engineer of record.
- Crane and hoisting left to the GC, which can be the largest single difference between bids.
- Miscellaneous metals, stairs and railings split out to a separate package without saying so.
- Shop primer included but field touch-up and galvanising repair excluded.