Shop drawings, connection design and the crane are where steel bids differ most.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Structural steel, furnish
  2. 2Structural steel, erect
  3. 3Metal deck
  4. 4Shear studs
  5. 5Connection design and engineering
  6. 6Shop drawings
  7. 7Miscellaneous metals and lintels
  8. 8Stairs and railings
  9. 9Crane and hoisting
  10. 10Shop primer and touch-up

Usual alternates

Compared side by side, never in the base total.

  • Fireproofing

Where structural steel bids differ

The gaps worth a written answer from every bidder before award.

  • Connection design and engineering excluded, or assumed to be done by the engineer of record.
  • Crane and hoisting left to the GC, which can be the largest single difference between bids.
  • Miscellaneous metals, stairs and railings split out to a separate package without saying so.
  • Shop primer included but field touch-up and galvanising repair excluded.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the structural steel template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.