CSI MasterFormat 07 10 00
Waterproofing and sealants scope checklist for bid levelling
Below-grade, air barrier and joint sealant scopes overlap with three or four other trades.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Below-grade waterproofing
- 2Air and vapour barrier
- 3Joint sealants, exterior
- 4Joint sealants, interior
- 5Firestopping
- 6Protection board
- 7Mock-up and testing
Where waterproofing and sealants bids differ
The gaps worth a written answer from every bidder before award.
- Joint sealants split between waterproofing, glazing and painting, with interior joints carried by nobody.
- Firestopping excluded and assumed to be by each MEP trade for its own penetrations.
- Protection board and mock-ups left out of below-grade and air barrier bids.
- Testing, such as flood tests and air barrier testing, assumed to be the owner's.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.