Earthwork and sitework scope checklist for bid levelling

Rock, unsuitable soils, dewatering and haul-off are where site bids diverge.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Clearing and grubbing
  2. 2Mass excavation
  3. 3Structural fill and compaction
  4. 4Export and haul-off
  5. 5Rock excavation
  6. 6Unsuitable soils removal
  7. 7Dewatering
  8. 8Erosion control and SWPPP
  9. 9Fine grading
  10. 10Building pad certification

Where earthwork and sitework bids differ

The gaps worth a written answer from every bidder before award.

  • Rock excavation and unsuitable soils excluded, or priced as unit rates with no quantity.
  • Export and haul-off limited to a fixed number of loads.
  • Dewatering excluded where the geotechnical report shows groundwater.
  • Building pad certification and testing assumed to be the owner's.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the earthwork and sitework template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.