CSI MasterFormat 03 00 00
Concrete scope checklist for bid levelling
By The GeneralBid team · Last reviewed
What should a concrete bid include?
Every concrete bid should price, include or explicitly exclude each of the 12 lines below, so the bids can be levelled like for like. Rebar, testing and winter protection are the lines most often assumed to be someone else's.
The concrete scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Footings and foundations
- 2Slab on grade
- 3Elevated slabs and decks
- 4Reinforcing steel, furnish and install
- 5Vapour barrier under slab
- 6Formwork and shoring
- 7Embeds and anchor bolts, set only
- 8Concrete pumping
- 9Cold and hot weather protection
- 10Sealer and curing compound
- 11Testing and inspection coordination
- 12Housekeeping pads
Usual alternates
Compared side by side, never in the base total.
- Polished concrete finish
What do concrete bids leave out?
The gaps worth a written answer from every bidder before award.
- Reinforcing steel priced as furnish-only, with placement assumed to be by the rebar sub or the GC.
- Cold and hot weather protection, heaters and blankets left out of the base price and billed as they are needed.
- Testing and inspection coordination assumed to be the owner's, including the cylinders and the lab scheduling.
- Pumping excluded where the site layout makes a pump unavoidable.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the concrete templateConcrete bid questions
What should a concrete bid include?
At least these 12 lines, each priced, included or excluded: footings and foundations; slab on grade; elevated slabs and decks; reinforcing steel, furnish and install; vapour barrier under slab; formwork and shoring; embeds and anchor bolts, set only; concrete pumping; cold and hot weather protection; sealer and curing compound; testing and inspection coordination; housekeeping pads. Add the lines your spec section calls for.
What do concrete subcontractor bids most often leave out?
Reinforcing steel priced as furnish-only, with placement assumed to be by the rebar sub or the GC. Cold and hot weather protection, heaters and blankets left out of the base price and billed as they are needed. Testing and inspection coordination assumed to be the owner's, including the cylinders and the lab scheduling. Pumping excluded where the site layout makes a pump unavoidable.
What CSI division is concrete?
Concrete is CSI MasterFormat 03 00 00. Use the spec section in that division to add project-specific lines to this checklist.
How do you level concrete bids?
Put every concrete bid against the same 12 scope lines. For each line, record a price, included, excluded or not mentioned. Price every excluded or unmentioned line with a plug (your estimate, or the median of the other bids), then rank the bids on their levelled totals and send each sub a clarification for its gaps.
What are the usual concrete alternates?
Polished concrete finish. Compare them side by side and keep them out of the base totals.
New to levelling? Read what bid leveling is and how to do it, or look up a term in the bid leveling glossary.