CSI MasterFormat 09 60 00
Flooring scope checklist for bid levelling
Floor preparation and moisture mitigation are the change orders waiting to happen.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Carpet tile
- 2Luxury vinyl tile
- 3Ceramic and porcelain tile
- 4Rubber base
- 5Floor preparation and levelling
- 6Moisture testing
- 7Moisture mitigation
- 8Transitions and trims
- 9Attic stock
Usual alternates
Compared side by side, never in the base total.
- Sealed concrete
Where flooring bids differ
The gaps worth a written answer from every bidder before award.
- Floor preparation and levelling excluded, or limited to minor patching.
- Moisture testing included but moisture mitigation excluded, which is where the cost is.
- Transitions, trims and rubber base split between flooring and other finishes.
- Attic stock quantities missing or different between bids.