CSI MasterFormat 07 50 00
Roofing scope checklist for bid levelling
Flashing, curbs and the manufacturer warranty vary more than the membrane price.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Roof membrane system
- 2Insulation and cover board
- 3Sheet metal flashing and coping
- 4Roof curbs and penetrations
- 5Roof drains and overflow, set only
- 6Walkway pads
- 7Manufacturer's warranty
- 8Hoisting
- 9Temporary roofing
Usual alternates
Compared side by side, never in the base total.
- 20-year warranty upgrade
Where roofing bids differ
The gaps worth a written answer from every bidder before award.
- Sheet metal flashing and coping excluded from membrane bids and carried as a separate trade.
- Curbs and penetrations flashed only for the units on the drawings, not those added by MEP.
- Warranty length and type differing between bids that otherwise look identical.
- Hoisting and temporary roofing assumed to be by the GC.