Flashing, curbs and the manufacturer warranty vary more than the membrane price.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Roof membrane system
  2. 2Insulation and cover board
  3. 3Sheet metal flashing and coping
  4. 4Roof curbs and penetrations
  5. 5Roof drains and overflow, set only
  6. 6Walkway pads
  7. 7Manufacturer's warranty
  8. 8Hoisting
  9. 9Temporary roofing

Usual alternates

Compared side by side, never in the base total.

  • 20-year warranty upgrade

Where roofing bids differ

The gaps worth a written answer from every bidder before award.

  • Sheet metal flashing and coping excluded from membrane bids and carried as a separate trade.
  • Curbs and penetrations flashed only for the units on the drawings, not those added by MEP.
  • Warranty length and type differing between bids that otherwise look identical.
  • Hoisting and temporary roofing assumed to be by the GC.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the roofing template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.