CSI MasterFormat 26 00 00
Electrical scope checklist for bid levelling
By The GeneralBid team · Last reviewed
What should a electrical bid include?
Every electrical bid should price, include or explicitly exclude each of the 12 lines below, so the bids can be levelled like for like. Low voltage, utility fees, temporary power and fire alarm swing electrical bids the most.
The electrical scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Service and distribution
- 2Branch wiring and devices
- 3Light fixtures, furnish and install
- 4Lighting controls
- 5Mechanical equipment connections
- 6Fire alarm system
- 7Low voltage rough-in and conduit
- 8Temporary power and lighting
- 9Utility company fees
- 10Site lighting
- 11Generator
- 12Permits and fees
Usual alternates
Compared side by side, never in the base total.
- EV charging
What do electrical bids leave out?
The gaps worth a written answer from every bidder before award.
- Low voltage rough-in and conduit excluded and assumed to be by the low voltage vendor.
- Utility company fees and transformer pads excluded.
- Temporary power and lighting priced for a shorter duration than the schedule.
- Fire alarm carried as an allowance on some bids and in full on others.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the electrical templateElectrical bid questions
What should a electrical bid include?
At least these 12 lines, each priced, included or excluded: service and distribution; branch wiring and devices; light fixtures, furnish and install; lighting controls; mechanical equipment connections; fire alarm system; low voltage rough-in and conduit; temporary power and lighting; utility company fees; site lighting; generator; permits and fees. Add the lines your spec section calls for.
What do electrical subcontractor bids most often leave out?
Low voltage rough-in and conduit excluded and assumed to be by the low voltage vendor. Utility company fees and transformer pads excluded. Temporary power and lighting priced for a shorter duration than the schedule. Fire alarm carried as an allowance on some bids and in full on others.
What CSI division is electrical?
Electrical is CSI MasterFormat 26 00 00. Use the spec section in that division to add project-specific lines to this checklist.
How do you level electrical bids?
Put every electrical bid against the same 12 scope lines. For each line, record a price, included, excluded or not mentioned. Price every excluded or unmentioned line with a plug (your estimate, or the median of the other bids), then rank the bids on their levelled totals and send each sub a clarification for its gaps.
What are the usual electrical alternates?
EV charging. Compare them side by side and keep them out of the base totals.
New to levelling? Read what bid leveling is and how to do it, or look up a term in the bid leveling glossary.