CSI MasterFormat 26 00 00
Levelling electrical bids in Atlanta, GA
Buying electrical for a project in Atlanta? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Low voltage, utility fees, temporary power and fire alarm swing electrical bids the most.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Service and distribution
- 2Branch wiring and devices
- 3Light fixtures, furnish and install
- 4Lighting controls
- 5Mechanical equipment connections
- 6Fire alarm system
- 7Low voltage rough-in and conduit
- 8Temporary power and lighting
- 9Utility company fees
- 10Site lighting
- 11Generator
- 12Permits and fees
Usual alternates
- EV charging
Where electrical bids differ
- Low voltage rough-in and conduit excluded and assumed to be by the low voltage vendor.
- Utility company fees and transformer pads excluded.
- Temporary power and lighting priced for a shorter duration than the schedule.
- Fire alarm carried as an allowance on some bids and in full on others.