CSI MasterFormat 26 00 00

Levelling electrical bids in Boston, MA

Buying electrical for a project in Boston? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Low voltage, utility fees, temporary power and fire alarm swing electrical bids the most.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Service and distribution
  2. 2Branch wiring and devices
  3. 3Light fixtures, furnish and install
  4. 4Lighting controls
  5. 5Mechanical equipment connections
  6. 6Fire alarm system
  7. 7Low voltage rough-in and conduit
  8. 8Temporary power and lighting
  9. 9Utility company fees
  10. 10Site lighting
  11. 11Generator
  12. 12Permits and fees

Usual alternates

  • EV charging

Where electrical bids differ

  • Low voltage rough-in and conduit excluded and assumed to be by the low voltage vendor.
  • Utility company fees and transformer pads excluded.
  • Temporary power and lighting priced for a shorter duration than the schedule.
  • Fire alarm carried as an allowance on some bids and in full on others.

Have the spec section?

The Bid Leveler can draft your scope lines from the project’s own spec, each with the paragraph it came from, so you level against what this job actually requires.

Open the Bid Leveler →

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or start from your spec section, paste from Excel, or pick a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal or spec you choose to have read, and does not store it, or a sheet you choose to save as a share link.