CSI MasterFormat 08 10 00

Doors, frames and hardware scope checklist for bid levelling

Install is often excluded from supply-only door bids, and electrified hardware from both.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Hollow metal frames
  2. 2Wood doors
  3. 3Hollow metal doors
  4. 4Finish hardware
  5. 5Installation
  6. 6Electrified hardware and power supplies
  7. 7Access control coordination
  8. 8Keying and cores

Usual alternates

Compared side by side, never in the base total.

  • Signage

Where doors, frames and hardware bids differ

The gaps worth a written answer from every bidder before award.

  • Supply-only bids with installation excluded, compared against supply-and-install bids.
  • Electrified hardware and power supplies excluded by the hardware supplier and by the electrician.
  • Keying and permanent cores left out, or priced for construction cores only.
  • Access control coordination assumed to be the security vendor's.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the doors, frames and hardware template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.