CSI MasterFormat 21 00 00
Fire protection scope checklist for bid levelling
Fire pump, backflow and design responsibility change the number more than the heads do.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Sprinkler mains and branch lines
- 2Heads and trim
- 3Design and hydraulic calcs
- 4Permits and fees
- 5Standpipes
- 6Fire pump
- 7Backflow preventer
- 8Fire department connection
- 9Testing and certification
Where fire protection bids differ
The gaps worth a written answer from every bidder before award.
- Design and hydraulic calculations excluded, or based on a flow test nobody has ordered.
- Fire pump and backflow preventer split between fire protection and plumbing.
- Permits and fees excluded and left to the GC.
- Fire department connection and standpipes priced by one bidder and not the others.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the fire protection template