CSI MasterFormat 23 00 00
HVAC scope checklist for bid levelling
By The GeneralBid team · Last reviewed
What should a hvac bid include?
Every hvac bid should price, include or explicitly exclude each of the 11 lines below, so the bids can be levelled like for like. Controls, test and balance, and structural supports are the recurring exclusions.
The hvac scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Rooftop units and equipment
- 2Ductwork
- 3Grilles, registers and diffusers
- 4Hydronic piping
- 5Controls and BAS
- 6Test and balance
- 7Duct insulation
- 8Equipment supports and curbs
- 9Crane and rigging
- 10Startup and commissioning support
- 11Permits and fees
Usual alternates
Compared side by side, never in the base total.
- Extended warranty
What do hvac bids leave out?
The gaps worth a written answer from every bidder before award.
- Controls and BAS excluded from the mechanical bid and bid separately by a controls vendor.
- Test and balance excluded, or assumed to be carried by the owner.
- Equipment supports, curbs and structural framing for rooftop units left to steel or roofing.
- Crane and rigging for rooftop equipment assumed to be the GC's.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the hvac templateHVAC bid questions
What should a hvac bid include?
At least these 11 lines, each priced, included or excluded: rooftop units and equipment; ductwork; grilles, registers and diffusers; hydronic piping; controls and bas; test and balance; duct insulation; equipment supports and curbs; crane and rigging; startup and commissioning support; permits and fees. Add the lines your spec section calls for.
What do hvac subcontractor bids most often leave out?
Controls and BAS excluded from the mechanical bid and bid separately by a controls vendor. Test and balance excluded, or assumed to be carried by the owner. Equipment supports, curbs and structural framing for rooftop units left to steel or roofing. Crane and rigging for rooftop equipment assumed to be the GC's.
What CSI division is hvac?
HVAC is CSI MasterFormat 23 00 00. Use the spec section in that division to add project-specific lines to this checklist.
How do you level hvac bids?
Put every hvac bid against the same 11 scope lines. For each line, record a price, included, excluded or not mentioned. Price every excluded or unmentioned line with a plug (your estimate, or the median of the other bids), then rank the bids on their levelled totals and send each sub a clarification for its gaps.
What are the usual hvac alternates?
Extended warranty. Compare them side by side and keep them out of the base totals.
New to levelling? Read what bid leveling is and how to do it, or look up a term in the bid leveling glossary.