HVAC scope checklist for bid levelling

Controls, test and balance, and structural supports are the recurring exclusions.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Rooftop units and equipment
  2. 2Ductwork
  3. 3Grilles, registers and diffusers
  4. 4Hydronic piping
  5. 5Controls and BAS
  6. 6Test and balance
  7. 7Duct insulation
  8. 8Equipment supports and curbs
  9. 9Crane and rigging
  10. 10Startup and commissioning support
  11. 11Permits and fees

Usual alternates

Compared side by side, never in the base total.

  • Extended warranty

Where hvac bids differ

The gaps worth a written answer from every bidder before award.

  • Controls and BAS excluded from the mechanical bid and bid separately by a controls vendor.
  • Test and balance excluded, or assumed to be carried by the owner.
  • Equipment supports, curbs and structural framing for rooftop units left to steel or roofing.
  • Crane and rigging for rooftop equipment assumed to be the GC's.

Level it instead of reading it

Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.

Open the hvac template

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or paste from Excel, or start from a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler

The levelling runs in your browser. GeneralBid only sees a proposal you choose to have read, and does not store it, or a sheet you choose to save as a share link.