CSI MasterFormat 23 00 00
HVAC scope checklist for bid levelling
Controls, test and balance, and structural supports are the recurring exclusions.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Rooftop units and equipment
- 2Ductwork
- 3Grilles, registers and diffusers
- 4Hydronic piping
- 5Controls and BAS
- 6Test and balance
- 7Duct insulation
- 8Equipment supports and curbs
- 9Crane and rigging
- 10Startup and commissioning support
- 11Permits and fees
Usual alternates
Compared side by side, never in the base total.
- Extended warranty
Where hvac bids differ
The gaps worth a written answer from every bidder before award.
- Controls and BAS excluded from the mechanical bid and bid separately by a controls vendor.
- Test and balance excluded, or assumed to be carried by the owner.
- Equipment supports, curbs and structural framing for rooftop units left to steel or roofing.
- Crane and rigging for rooftop equipment assumed to be the GC's.