CSI MasterFormat 06 10 00
Rough carpentry scope checklist for bid levelling
Blocking for other trades is the classic gap: everyone assumes carpentry carries it.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Wood framing
- 2Sheathing
- 3Blocking for other trades
- 4Roof trusses, furnish and set
- 5Hardware and hold-downs
- 6Temporary protection and barricades
- 7Fire-treated lumber where required
- 8Engineered lumber
Where rough carpentry bids differ
The gaps worth a written answer from every bidder before award.
- Blocking for other trades: casework, grab bars, TVs and equipment, assumed to be someone else's.
- Fire-treated lumber priced as standard where the code or the drawings call for it.
- Hold-downs and hardware supplied by the truss or lumber supplier and installed by nobody.
- Temporary protection and barricades left to the GC's general conditions.
Level it instead of reading it
Open this checklist in the Bid Leveler, type or paste each bid against it, and every gap is priced, every bid ranked like for like, and a clarification email written for each sub. Free, in your browser.
Open the rough carpentry template