CSI MasterFormat 06 10 00
Levelling rough carpentry bids in Seattle, WA
Buying rough carpentry for a project in Seattle? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Blocking for other trades is the classic gap: everyone assumes carpentry carries it.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Wood framing
- 2Sheathing
- 3Blocking for other trades
- 4Roof trusses, furnish and set
- 5Hardware and hold-downs
- 6Temporary protection and barricades
- 7Fire-treated lumber where required
- 8Engineered lumber
Where rough carpentry bids differ
- Blocking for other trades: casework, grab bars, TVs and equipment, assumed to be someone else's.
- Fire-treated lumber priced as standard where the code or the drawings call for it.
- Hold-downs and hardware supplied by the truss or lumber supplier and installed by nobody.
- Temporary protection and barricades left to the GC's general conditions.
Have the spec section?
The Bid Leveler can draft your scope lines from the project’s own spec, each with the paragraph it came from, so you level against what this job actually requires.