CSI MasterFormat 08 10 00
Levelling doors, frames and hardware bids in Seattle, WA
Buying doors, frames and hardware for a project in Seattle? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Install is often excluded from supply-only door bids, and electrified hardware from both.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Hollow metal frames
- 2Wood doors
- 3Hollow metal doors
- 4Finish hardware
- 5Installation
- 6Electrified hardware and power supplies
- 7Access control coordination
- 8Keying and cores
Usual alternates
- Signage
Where doors, frames and hardware bids differ
- Supply-only bids with installation excluded, compared against supply-and-install bids.
- Electrified hardware and power supplies excluded by the hardware supplier and by the electrician.
- Keying and permanent cores left out, or priced for construction cores only.
- Access control coordination assumed to be the security vendor's.
Have the spec section?