CSI MasterFormat 21 00 00
Levelling fire protection bids in Phoenix, AZ
Buying fire protection for a project in Phoenix? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Fire pump, backflow and design responsibility change the number more than the heads do.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Sprinkler mains and branch lines
- 2Heads and trim
- 3Design and hydraulic calcs
- 4Permits and fees
- 5Standpipes
- 6Fire pump
- 7Backflow preventer
- 8Fire department connection
- 9Testing and certification
Where fire protection bids differ
- Design and hydraulic calculations excluded, or based on a flow test nobody has ordered.
- Fire pump and backflow preventer split between fire protection and plumbing.
- Permits and fees excluded and left to the GC.
- Fire department connection and standpipes priced by one bidder and not the others.
Have the spec section?
The Bid Leveler can draft your scope lines from the project’s own spec, each with the paragraph it came from, so you level against what this job actually requires.
Open the Bid Leveler →