Buying structural steel for a project in Philadelphia? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Shop drawings, connection design and the crane are where steel bids differ most.
The scope lines
Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.
- 1Structural steel, furnish
- 2Structural steel, erect
- 3Metal deck
- 4Shear studs
- 5Connection design and engineering
- 6Shop drawings
- 7Miscellaneous metals and lintels
- 8Stairs and railings
- 9Crane and hoisting
- 10Shop primer and touch-up
Usual alternates
- Fireproofing
Where structural steel bids differ
- Connection design and engineering excluded, or assumed to be done by the engineer of record.
- Crane and hoisting left to the GC, which can be the largest single difference between bids.
- Miscellaneous metals, stairs and railings split out to a separate package without saying so.
- Shop primer included but field touch-up and galvanising repair excluded.