CSI MasterFormat 05 12 00

Levelling structural steel bids in Charlotte, NC

Buying structural steel for a project in Charlotte? Whatever the city, the bids that look cheapest are usually the ones that leave something out. Shop drawings, connection design and the crane are where steel bids differ most.

The scope lines

Ask every bidder to say, for each line, whether it is priced, included, or excluded. A line a bid never mentions is the one that turns into a change order.

  1. 1Structural steel, furnish
  2. 2Structural steel, erect
  3. 3Metal deck
  4. 4Shear studs
  5. 5Connection design and engineering
  6. 6Shop drawings
  7. 7Miscellaneous metals and lintels
  8. 8Stairs and railings
  9. 9Crane and hoisting
  10. 10Shop primer and touch-up

Usual alternates

  • Fireproofing

Where structural steel bids differ

  • Connection design and engineering excluded, or assumed to be done by the engineer of record.
  • Crane and hoisting left to the GC, which can be the largest single difference between bids.
  • Miscellaneous metals, stairs and railings split out to a separate package without saying so.
  • Shop primer included but field touch-up and galvanising repair excluded.

Have the spec section?

The Bid Leveler can draft your scope lines from the project’s own spec, each with the paragraph it came from, so you level against what this job actually requires.

Open the Bid Leveler →

Drop in every proposal. Get one levelled sheet.

Drop in the sub proposals as PDFs or pasted email text and review each one line by line before it goes in, or start from your spec section, paste from Excel, or pick a trade template. See every exclusion priced, the real low bid, and a clarification email for each sub. Free. No account, no card, no call.

Open the Bid Leveler